Japan’s sixth solar auction concludes with lowest bid of $0.095/kWh

Around 368.8 MW of PV projects were allocated in the sixth round of Japan’s procurement program for large-scale solar. The lowest price offered was ¥10.00/kWh ($0.095) and the highest ¥12.00, for an average price of ¥11.49.

Japan’s Ministry of Economy, Trade and Industry (METI) has announced the results of the sixth auction for solar projects with a generation capacity of more than 250 kW.

The ministry said it has selected solar power projects with a combined capacity of 368.8 MW in the procurement exercise, after having initially accepted project proposals with a combined capacity of 526.5 MW for review.

The METI had originally planned to allocate around 750 MW of solar capacity in the auction and had set a ceiling price of ¥12.00 ($0.114)/kWh.

The 255 selected projects have a capacity ranging from 300 kW to 68.6 MW.

Slight decrease in average price

The METI has also revealed that in the procurement exercise the lowest price offered was ¥10.00/kWh ($0.095) and the highest ¥12.0 for an average price of ¥12.57.

In the fifth auction held in January, the lowest price offered was ¥10.99/kWh and the highest ¥13.0, for an average price of ¥12.57. The METI selected solar power projects with a combined capacity of only 39.8 MW in the procurement exercise, after having initially accepted 72 project proposals with a combined capacity of 185.6 MW for review.

In the fourth auction held in the summer of 2019, the lowest price was ¥10.50/kWh ($0.0988), while the highest price was ¥13.99 and the average price was ¥12.98.

In the third auction finalized in January 2019, the METI had selected seven projects with a total capacity of 196.6 MW. Average price was ¥15.01 ($0.137) per kWh, with the lowest bid ¥14.25 and the highest ¥15.45.

The second auction, in September 2018, was a bit more successful in terms of capacity, with around 197 MW and a lowest bid of ¥16.47. In another under-subscribed first auction held in November 2017, only 140 MW of a hoped-for 500 MW of capacity was awarded, at an average price of ¥11.49/kWh.

The main issue solar developers have to address in Japan is land availability – in part due to restrictions on the use of abandoned agricultural sites – and grid constraints.


Lắp đặt điện mặt trời Khải Minh Tech
https://ift.tt/2X7bF6x
0906633505
info.khaiminhtech@gmail.com
80/39 Trần Quang Diệu, Phường 14, Quận 3
Lắp đặt điện mặt trời Khải Minh Tech
https://ift.tt/2ZH4TRU

Không có nhận xét nào:

Đăng nhận xét